Language-agnostic AI knowledge registry for Technical Project Management, PRDs, PRD review, Software Architecture planning, Task breakdown, Estimation, Risk assessment, Status reporting, Backlog prioritization, Sprint planning, Retrospectives, and Agile ticket generation. Uses Markdown + Front-matter architecture.

95

1.03x
Quality

97%

Does it follow best practices?

Impact

95%

1.03x

Average score across 10 eval scenarios

SecuritybySnyk

Passed

No known issues

Overview
Quality
Evals
Security
Files

SKILL.mdskills/execution/generate-status-report/

name:
generate-status-report
license:
MIT
description:
Generates a stakeholder status report from task data — never fabricate progress mark unknowns as "needs update", include Executive Summary (health key accomplishment top concern) then accomplishments in-progress blockers risks and next steps, verify no status is fabricated or assumed. Language-agnostic. Trigger words: status report, sprint update, stakeholder update, progress report, weekly update, project status.
metadata:
{"version":"1.0.0","user-invocable":"true"}

Generating a Status Report

Produce a clear, honest status report. Focus on progress, blockers, and what's next.

HARD-GATE

DO NOT fabricate or assume progress. Unknown → "Status unknown — needs update."
DO NOT hide blockers or risks to make the report look better.
DO NOT use passive language ("was delayed" → "Blocked on Y, owner: Z").

Core Process

  • Input: Task progress, sprint info, blocker list, risk register (optional).
  • Output: Structured markdown report with sections: Executive Summary, Accomplishments, In Progress, Blocked, Risks, Next Steps.
  • Rule: Never fabricate progress — mark unknowns as "needs update."
  1. Gather — task progress, sprint info, blocker list, optional risk register.
  2. Categorize — Accomplished, In Progress, Blocked, Upcoming.
  3. Write Executive Summary — 2-4 sentences: health, key accomplishment, top concern.
  4. Fill template — follow the STATUS_REPORT_TEMPLATE below, section by section.
  5. Review — verify no status is fabricated or assumed.

STATUS_REPORT_TEMPLATE

# Status Report: [Project / Sprint Name]
**Period:** [Start Date] – [End Date]   **Prepared:** [Date]   **Author:** [Name]

## Executive Summary
**Health:** On Track | At Risk | Blocked
[2-4 sentences: overall health, key accomplishment, top concern.]

## Accomplishments
- [Task / milestone completed] — [brief context, e.g., "merged PR #42, closes Auth epic"]
- …

## In Progress
| Task | Owner | Status | ETA |
|------|-------|--------|-----|
| [Task name] | [Owner] | [% or narrative] | [Date] |

## Blocked
| Task | Blocker | Owner | Resolution Plan |
|------|---------|-------|------------------|
| [Task name] | [Specific blocker description] | [Owner] | [Next action + target date] |

## Risks & Concerns
| # | Risk | Likelihood | Impact | Status Change |
|---|------|-----------|--------|---------------|
| 1 | [Risk description] | High/Med/Low | High/Med/Low | New / Unchanged / Resolved |

## Next Steps
- [Action] — Owner: [Name], Due: [Date]
- …

Concrete Example

Sample input (provided by user or gathered from context):

Sprint 14 | May 6–10 2025
Done: Deploy auth service to staging (owner: Ana)
In Progress: API rate-limiting (owner: Ben, 60%, ETA May 10); Dashboard redesign (owner: Cara, 30%, ETA May 14)
Blocked: Payment integration — third-party API keys not received, owner: Dan, escalated to procurement May 7
Risk: Rate-limiting miss could delay beta by one week

Resulting report excerpt:

# Status Report: Sprint 14
**Period:** May 6–10 2025   **Prepared:** May 10 2025   **Author:** Agent

## Executive Summary
**Health:** At Risk
Auth service is deployed to staging on schedule. API rate-limiting is on track for
Friday but payment integration is blocked pending third-party credentials, putting the
beta timeline at risk by up to one week.

## Accomplishments
- Auth service deployed to staging — closes Sprint 13 carry-over (owner: Ana)

## In Progress
| Task | Owner | Status | ETA |
|------|-------|--------|-----|
| API rate-limiting | Ben | 60% | May 10 |
| Dashboard redesign | Cara | 30% | May 14 |

## Blocked
| Task | Blocker | Owner | Resolution Plan |
|------|---------|-------|------------------|
| Payment integration | Third-party API keys not received | Dan | Escalated to procurement May 7; follow up May 10 |

## Risks & Concerns
| # | Risk | Likelihood | Impact | Status Change |
|---|------|-----------|--------|---------------|
| 1 | Rate-limiting slip delays beta | Medium | High | New |

## Next Steps
- Confirm API keys received — Owner: Dan, Due: May 10
- Complete rate-limiting — Owner: Ben, Due: May 10

Integration

SkillWhen to chain
identify-risksInclude latest risk register in the status report
estimate-tasksReference estimates when reporting vs planned effort
product-ownerReport on PRD-aligned scope and scope changes

skills

execution

generate-status-report

CODE_OF_CONDUCT.md

CONTRIBUTING.md

README.md

tile.json