Language-agnostic AI knowledge registry for Technical Project Management, PRDs, PRD review, Software Architecture planning, Task breakdown, Estimation, Risk assessment, Status reporting, Backlog prioritization, Sprint planning, Retrospectives, and Agile ticket generation. Uses Markdown + Front-matter architecture.

95

1.03x
Quality

97%

Does it follow best practices?

Impact

95%

1.03x

Average score across 10 eval scenarios

SecuritybySnyk

Passed

No known issues

Overview
Quality
Evals
Security
Files

SKILL.mdskills/execution/identify-risks/

name:
identify-risks
license:
MIT
description:
Scans plans for risks backed by evidence not speculation — check dependency chains single points of failure ambiguous requirements external dependencies capacity and technical uncertainty, do not fabricate risks and every risk MUST reference a specific task or requirement as evidence, classify each risk with Likelihood Impact and Proximity, verify likelihood and impact ratings are justified by evidence, and include concrete mitigations. Language-agnostic. Use when asked about risks, risk assessment, blockers, what could go wrong, or to produce a risk register for a plan, PRD, ticket set, or sprint.
metadata:
{"version":"1.0.0","user-invocable":"true"}

Identifying Project Risks

Scan plans for risks backed by concrete evidence — not speculation.

Quick Reference

  • Input: Task list, PRD, ticket set, or sprint plan.
  • Output: Risk register (description, likelihood, impact, mitigation).
  • Rule: Every risk cites specific evidence from the plan.

HARD-GATE

DO NOT fabricate risks. Every risk MUST reference a specific task or requirement.
DO NOT flag everything as high-risk — use the likelihood/impact matrix honestly.
DO NOT skip mitigations — every risk needs at least one concrete mitigation.

Core Process

  1. Receive — task list, PRD, ticket set, or sprint plan.
  2. Scan risk patterns (see Risk Patterns below) — dependency chains, external deps, ambiguity, single points of failure, capacity, technical uncertainty.
  3. Classify — Likelihood (High/Medium/Low), Impact (High/Medium/Low), Proximity (Immediate/Near-term/Future).
  4. Suggest mitigations — prevention, contingency, owner.
  5. Validate — cross-check each risk against the plan:
    • Remove any risk that lacks direct evidence from the source material
    • Flag gaps where patterns apply but no risk was identified
    • Verify likelihood/impact ratings are justified by evidence
  6. Output — structured risk register.

Risk Patterns

Apply these six patterns when scanning the plan:

#PatternSignals
1Dependency ChainTask B cannot start until Task A completes; A is not yet done
2Single Point of FailureOnly one person owns a critical path item; no documented backup
3Ambiguous RequirementAcceptance criteria missing, TBD placeholders, or vague verbs ("improve", "enhance")
4External DependencyThird-party API, vendor delivery, regulatory approval, or customer sign-off required
5Capacity / ResourceTeam member over-allocated; holiday or leave overlaps delivery window
6Technical UncertaintyNew technology, unproven integration, or no spike/prototype yet planned

Concrete Example

Sample input task: "Integrate payment gateway — assigned to Alice, go-live Friday. Vendor sandbox access not yet confirmed."

Resulting risk register row:

IDRiskLikelihoodImpactProximityEvidenceMitigation
R1Payment gateway integration blocked by missing vendor sandbox accessHighHighImmediateTask: "Vendor sandbox access not yet confirmed"Owner: Alice escalates to vendor by EOD Monday; contingency: mock server for internal testing until access granted

Output Style

  1. Risk Register| ID | Risk | Likelihood | Impact | Proximity | Evidence | Mitigation |
  2. Summary — count by severity and proximity.
  3. Top 3 risks — detailed mitigation recommendations.
  4. Assumptions — about team, timeline, or external factors.
  5. English only unless user requests otherwise.

Integration

SkillWhen to chain
estimate-tasksAfter estimation, assess risks from high-uncertainty tasks
generate-tasksAfter task breakdown, identify dependency risks
generate-status-reportInclude risk updates in stakeholder status reports