Implementation Planner — Worked Examples

Example: URL Shortener plan (Mode 1)

Given: PRD for a URL shortener with REST API, SQLite storage, and a health check.

Scope analysis: 3 natural phases (bootstrap → core logic → API + health).

sh scripts/new-plan.sh url-shortener-service
sh scripts/new-phase.sh url-shortener-service 01 workspace-bootstrap
sh scripts/new-task.sh url-shortener-service 01 01 initialise-npm-package
sh scripts/new-task.sh url-shortener-service 01 02 configure-typescript
sh scripts/new-phase.sh url-shortener-service 02 database-layer
sh scripts/new-task.sh url-shortener-service 02 01 create-sqlite-schema
sh scripts/new-task.sh url-shortener-service 02 02 implement-url-repository
sh scripts/new-phase.sh url-shortener-service 03 http-api
sh scripts/new-task.sh url-shortener-service 03 01 post-shorten-endpoint
sh scripts/new-task.sh url-shortener-service 03 02 get-redirect-endpoint
sh scripts/new-task.sh url-shortener-service 03 03 health-check-endpoint
sh scripts/validate-plan.sh url-shortener-service

Task task-P03T01-post-shorten-endpoint.md verification:

npm start &; sleep 1
curl -sf -X POST http://localhost:3000/shorten \
  -H 'Content-Type: application/json' \
  -d '{"url":"https://example.com"}' | jq -e '.code | length == 6'
kill %1

Example: Scope exceeds 8 phases

PRD covers auth, ingestion, pipeline, storage, query, viz, multi-tenancy, ops, DX (9 domains).

Step 2, action 1: Count natural phases = 9. Count ≥ 9 → guardrail triggered.

Correct behaviour: Stop immediately. Zero scripts run. Zero files created. Send this message to the user and wait:

I've counted 9 natural phases from the requirements. I need your input before I create any files:

A. Split into two plans: plan-platform-core (auth, ingestion, pipeline, storage, query) and plan-platform-surface (viz, multi-tenancy, ops, DX)

B. Consolidate to 7 phases: merge storage+query into one phase and ops+DX into one (→ 7 phases total)

C. Proceed with all 9 phases in a single plan

Which would you prefer?

Wrong behaviour — do not do any of these:

  • Counting 9 phases but designing only 8 and omitting auth or DX
  • Running new-plan.sh before receiving the user's answer
  • Creating some phases then mentioning the limit
  • Asking the question inside a code comment or after file creation

Example: Restructure migration plan (Mode 2)

Source: docs/migration-plan.md with 5 numbered sections, ~35 items.

Scope analysis: 5 phases, 4–9 items each — within the 3–7 sweet spot for most.

docs/refactoring/phases/
  phase-1-codebase-analysis/           # 4 items → flat under activities/
    README.md
    activities/
      activity-1.1-dependency-graph.md
      activity-1.2-bounded-contexts.md
      activity-1.3-shared-libraries.md
      activity-1.4-data-ownership.md
  phase-3-user-service-extraction/     # 9 items → consider grouping
    README.md
    activities/
      group-a-implementation/          # 5 items (3.1–3.5)
        activity-3.1-copy-domain.md
        ...
      group-b-rollout/                 # 4 items (3.6–3.9)
        activity-3.6-deploy-staging.md
        ...