Dependency Analysis

How to build a task dependency DAG and assign tasks to waves.

Step 1 — Extract tasks

List every task with:

  • ID — short identifier (T1.1, P0, phase-3, etc.)
  • Description — what the task does
  • Dependencies — IDs of tasks that must complete first (empty = none)

If dependencies are not stated in the source document, infer them:

Signal in sourceInferred dependency
"after X is done" / "once X lands"task depends on X
"requires X to exist"task depends on X
Test task for feature Fdepends on F implementation
Merge / cleanup taskdepends on all tasks being merged
Validation taskdepends on all implementation tasks
Deployment taskdepends on validation task
Tasks touching the same filesequential dependency on earlier task
Tasks touching independent filesno dependency (can be parallel)
Infrastructure task removes a resource (config value, secret, permission grant, env var, queue) that the live application still reads at runtimeboth the infrastructure removal and the consumer code removal must land together — flag for Step 5
New code requires a resource (env var, schema column, API endpoint) that does not yet exist in the deployed environmentboth the resource-creation task and the consumer code task must land together, or the resource-creation wave must precede the consumer wave — flag for Step 5
A task changes an interface (API contract, event schema, DB column type) in a way that is incompatible with existing consumersuse expand-contract sequencing: Wave N adds the new alongside the old, Wave N+1 migrates consumers, Wave N+2 removes the old — flag for Step 5

Step 2 — Build the DAG

Represent the graph as an adjacency list:

T1.1 → []          (no dependencies)
T1.2 → []
T2.1 → [T1.1]      (depends on T1.1)
T2.2 → [T1.2]
T3.1 → [T2.1, T2.2]

Check for cycles — a cycle means the requirements are contradictory. Surface this to the user before proceeding.

Step 3 — Assign waves (topological sort)

Wave(task) = 1                              if task has no dependencies
Wave(task) = 1 + max(Wave(dep) for dep in dependencies)

All tasks with the same wave number can execute concurrently.

Example:

T1.1 deps=[]       → Wave 1
T1.2 deps=[]       → Wave 1
T1.3 deps=[]       → Wave 1
T2.1 deps=[T1.1]   → Wave 2   (1 + max(1) = 2)
T2.2 deps=[T1.1, T1.2] → Wave 2
T3.1 deps=[T2.1]   → Wave 3
T3.2 deps=[T2.1, T2.2] → Wave 3
T4.1 deps=[T3.1, T3.2] → Wave 4

Step 4 — Label waves

Give each wave a short descriptive label:

PatternExample label
Diagnostics / audits"Diagnostics & Design"
Setup / scaffolding"Bootstrap & Extract"
Core implementation"Fix & Build"
Tests / coverage"Coverage & Validation"
Integration / merge"Integration & Wrap-up"
Pre-requisites"Pre-work"
Final checks / PR"Wrap-up"

Step 5 — Decide parallel vs sequential

A wave is parallel when:

  • It contains 2 or more tasks that touch different files/modules, AND
  • There is no ordering constraint among those tasks.

A wave is sequential when:

  • It contains only 1 task, OR
  • Tasks within the wave must run in a specific order (e.g. "apply migration THEN verify"), OR
  • A critical shared resource prevents concurrent work (e.g. single CloudFormation stack).

A wave is must land together when:

  • Tasks within the wave must be committed/deployed atomically because any intermediate deployed state would break a live service.

How to detect it: For every wave boundary, ask: "If this wave deploys and the next has not landed yet, does any existing functionality break?" If yes, tasks on both sides must be in the same must land together wave. Three patterns trigger this:

PatternBroken intermediate stateFix
Stranded consumerA resource (config, env var, permission, queue) is removed in Wave N; code that still reads it is only removed in Wave N+1Merge both tasks into one must-land-together wave
Premature consumerCode that requires a new resource (env var, schema column, API endpoint) ships in Wave N; the resource is created in Wave N+1Create the resource first (earlier wave), or merge into must-land-together
Breaking contractAn API, event schema, or DB column changes incompatibly in Wave N; consumers that rely on the old contract are only updated in Wave N+1Use expand-contract sequencing: add new alongside old → migrate consumers → remove old

Common triggers:

  • Removing a configuration value, secret, or permission grant that the live service reads at startup or runtime
  • Removing a queue, topic, or storage resource that the live service publishes or reads from
  • Deploying a service that reads a new required env var before that variable is provisioned
  • Adding a NOT NULL database column before the code that writes to it is deployed
  • Changing an API contract (removing a field or endpoint) before all consumers are updated

Note: the code-level dependency graph will NOT catch these. Runtime dependencies have no source imports, so a naive topological sort assigns the tasks to different waves. You must reason about the deployed runtime state, not the source tree.

Step 6 — Assign branches

For parallel waves, assign one branch per workstream:

<type>/<scope>-<slug>

Examples:

  • refactor/scripts-lib-http
  • feat/phase-3-clean-lambda
  • test/baseline
  • ci/deployment-automation

For sequential waves, one branch covers the whole wave:

<type>/<wave-label-slug>

DAG diagram format

Emit in the Dependency Graph section of the wave document:

Wave 1 (parallel)
  T1.1 <description> ─┐
  T1.2 <description> ─┤─► Wave 2
  T1.3 <description> ─┘

Wave 2 (parallel, unblocked after Wave 1)
  T2.1 <description> (← T1.1) ─┐
  T2.2 <description> (← T1.2) ─┤─► Wave 3
  T2.3 <description> (← T1.3) ─┘

Wave 3 (sequential)
  T3.1 <description> (← all Wave 2)

Rules:

  • Use ─┐, ─┤, ─┘ for parallel merges.
  • Use (← X) to annotate the specific dependency.
  • Use ─► to show the wave that unblocks.

Edge cases

Task with many dependents

If T1.1 is a prerequisite for 10 tasks, those 10 tasks are still all Wave 2 — they just all depend on T1.1. Do not create an intermediate wave just to "stage" them.

Circular dependency detected

Surface to user:

ERROR: Circular dependency detected: T2.1 → T3.1 → T2.1
Cannot assign wave numbers until this is resolved.
Suggested fix: [description of how to break the cycle]

Tasks with unknown dependencies

When a task says "depends on the above" without specifying, treat it as depending on all tasks earlier in the same phase/section.

Large waves (>5 tasks)

Split large parallel waves into sub-groups by semantic domain, keeping them in the same wave number. Use phase rows in the table to separate the groups visually.

Unsafe intermediate deploy states

The naive topological sort assigns waves based on code-level imports. It cannot detect runtime dependencies. Three patterns produce an unsafe intermediate state; all require manual correction.

Stranded consumer

When a wave removes an infrastructure resource AND a later wave removes the consumer code that still references it, deploying the first wave alone breaks the live service.

Fix: merge both tasks into the same must-land-together wave. They can be worked in parallel worktrees but must deploy together.

Example (decommissioning a third-party SDK):

WRONG — separate waves:
  Wave 2: remove config parameter, permission grant, env var   (infrastructure)
  Wave 3: remove SDK client & dead code paths                  (application code)
  → Deploying Wave 2 alone breaks the live service

CORRECT — same wave:
  Wave 2 (must land together):
    Phase 1: remove config parameter, permission grant, env var   (infrastructure)
    Phase 2: remove SDK client & dead code paths                  (application code)
  > Phases 1 and 2 must deploy atomically.

Premature consumer

When a wave deploys code that depends on a resource that does not yet exist in the environment (new required env var, NOT NULL schema column, new API endpoint), the service fails on startup or at the call site.

Fix: either create the resource in an earlier wave (safe default), or merge resource-creation and consumer into a single must-land-together wave.

Example (adding a required external API key):

WRONG — consumer first:
  Wave 1: deploy service code that reads NEW_API_KEY env var
  Wave 2: provision NEW_API_KEY in the environment
  → Wave 1 fails at startup: env var missing

CORRECT — resource first:
  Wave 1: provision NEW_API_KEY in the environment
  Wave 2: deploy service code that reads NEW_API_KEY

Breaking contract change

When a wave changes an interface (REST endpoint shape, event schema, DB column type) in a way that is incompatible with current consumers, deploying the change alone breaks every caller that has not yet been updated.

Fix: use expand-contract sequencing across three waves. Never remove the old version until all consumers have migrated.

Example (renaming an API field):

WRONG — big-bang:
  Wave 2: rename field user_id → userId in both API and all consumers
  → Any consumer not yet deployed breaks

CORRECT — expand-contract:
  Wave 2: API emits both user_id and userId (backwards-compatible)
  Wave 3: migrate all consumers to read userId
  Wave 4: remove user_id from the API response