CtrlK
BlogDocsLog inGet started
Tessl Logo

project-sizing-guide

Software project effort estimation assistant. Outputs three-point estimates (optimistic/most-likely/pessimistic values with confidence intervals), T-shirt sizes, or Function Point Analysis (FPA) counts. Triggered when users ask 'how long will this feature take,' need to assess project workload, perform PERT estimation, T-shirt sizing, FPA, sprint planning, or quote-based effort breakdowns.

72

Quality

88%

Does it follow best practices?

Run evals on this skill

Adds up to 20 points to the overall score

View guide

SecuritybySnyk

Passed

No findings from the security scan

SKILL.md
Quality
Evals
Security

Project Sizing Guide — Software Project Effort Estimation

Helps teams produce scientifically grounded effort estimates for software projects, based on three major methodologies: Three-Point Estimation (PERT), T-shirt Sizing, and Function Point Analysis (FPA). Outputs optimistic, most-likely, and pessimistic values along with risk intervals.

Quick Start

  1. User provides a requirements description → Agent identifies functional modules and breaks them into a Work Breakdown Structure (WBS)
  2. Select an estimation method → Choose the best-fit approach based on project stage and available information
  3. Estimate each item → Assign O/M/P (Optimistic / Most Likely / Pessimistic) values to every work package
  4. Aggregate and report → Generate an estimation report with risk analysis and confidence intervals

A calculation helper is available:

python3 scripts/estimate_calculator.py --method pert --tasks '[{"name":"User Login","O":2,"M":3,"P":8}]'

Method Selection Guide

ScenarioRecommended MethodRationale
Early feasibility study, rough budgetingT-shirt SizingLittle information available; quickly align on order of magnitude
Sprint planning, iteration estimationThree-Point Estimation (PERT)Good granularity with confidence intervals
Contract bidding, large-project RFPsFunction Point Analysis (FPA)Most rigorous; industry-comparable
Team has historical dataPERT + historical calibrationCombines empirical correction with data

Method 1: Three-Point Estimation (PERT)

Core Formulas

MetricFormulaMeaning
Expected Value E(O + 4M + P) / 6Weighted average effort
Standard Deviation σ(P − O) / 6Estimation uncertainty
Variance Vσ²Used to aggregate across tasks
Project Total ExpectedΣESum of individual expected values
Project Total Std Dev√(ΣV)Square root of summed variances

Where:

  • O (Optimistic): Shortest duration assuming everything goes smoothly
  • M (Most Likely): Duration under normal circumstances
  • P (Pessimistic): Longest duration when significant difficulties arise

Confidence Intervals

Confidence LevelIntervalUse Case
68.3%E ± 1σInternal rough estimates
90%E ± 1.645σProject planning
95%E ± 2σExternal quotes
99.7%E ± 3σContractual commitments

Steps

  1. Build the WBS: Decompose requirements into the smallest independently estimable units (recommended ≤ 5 person-days each)
  2. Three-point estimation: For each work package, provide O / M / P values (use consistent units: person-hours or person-days)
  3. Calculate per-task expected value and standard deviation
  4. Aggregate project-level metrics: Total Expected = ΣE, Total Std Dev = √(Σσ²)
  5. Output confidence intervals: Choose a confidence level based on risk appetite

O/M/P Estimation Rules of Thumb

  • O should not be less than 30% of M (overly optimistic suggests essential steps were overlooked)
  • P should not exceed 5× M (overly pessimistic suggests unclear requirements that need clarification first)
  • If O ≈ M ≈ P, the task is either extremely well-understood or the estimator hasn't seriously considered risks
  • The P/O ratio (spread ratio) reflects uncertainty: < 2 = low risk, 2–4 = medium risk, > 4 = high risk

Method 2: T-shirt Sizing

Size Reference Table

SizeTypical Range (person-days)Typical Story PointsSuitable For
XS0.25 – 0.51Config changes, copy edits, simple bug fixes
S0.5 – 22 – 3Single-component development, simple API, minor UI tweaks
M2 – 55 – 8Complete feature module, moderately complex API
L5 – 1513 – 21Cross-module features requiring integration
XL15 – 4034 – 55Subsystem-level development requiring architecture design
XXL40+89+Should be split across multiple iterations; not recommended as a single estimation unit

Converting T-shirt Sizes to Three-Point Estimates

When more precise numbers are needed, T-shirt sizes can be converted to three-point estimates:

SizeO (person-days)M (person-days)P (person-days)
XS0.250.51
S0.512.5
M23.57
L51020
XL152550
XXL4070150

Steps

  1. Team alignment: Confirm what each size means (the table above is a reference; teams may customize)
  2. Independent assessment: Each person assigns a size independently to avoid anchoring bias
  3. Discuss discrepancies: When estimates differ by more than 2 sizes, a discussion is mandatory
  4. Reach consensus: Adopt the team consensus value
  5. Convert to numbers (optional): Use the table above to derive O/M/P values

Method 3: Function Point Analysis (FPA)

Five Function Component Types

Component TypeAbbreviationDefinitionExample
Internal Logical FileILFLogical data group maintained by the applicationUsers table, Orders table
External Interface FileEIFData group referenced but not maintained by the applicationThird-party exchange rate data
External InputEIData processing entering the system from outsideForm submission, API POST
External OutputEOData generated and sent outside the systemReport generation, exports
External InquiryEQSimple data retrieval + displayList queries, detail pages

Complexity Weight Matrix

Component TypeLowMediumHigh
ILF71015
EIF5710
EI346
EO457
EQ346

Complexity Assessment Rules

ILF / EIF Complexity (based on DET – Data Element Types and RET – Record Element Types):

DET 1-19DET 20-50DET 51+
RET 1LowLowMedium
RET 2-5LowMediumHigh
RET 6+MediumHighHigh

EI Complexity (based on DET and FTR – File Types Referenced):

DET 1-4DET 5-15DET 16+
FTR 0-1LowLowMedium
FTR 2LowMediumHigh
FTR 3+MediumHighHigh

EO / EQ Complexity (based on DET and FTR):

DET 1-5DET 6-19DET 20+
FTR 0-1LowLowMedium
FTR 2-3LowMediumHigh
FTR 4+MediumHighHigh

Converting Function Points to Effort

After calculating Unadjusted Function Points (UFP):

  1. Calculate the Value Adjustment Factor (VAF) (optional; deprecated since IFPUG 4.3+ but still used by some teams)

    • 14 General System Characteristics (GSC), each scored 0–5
    • VAF = 0.65 + 0.01 × Σ(GSC)
    • Adjusted Function Points AFP = UFP × VAF
  2. Function points to person-hours

    • Industry benchmark: 8–15 person-hours per function point (varies by language and team maturity)
    Technology StackPerson-hours / FPNotes
    Low-code / Mature Frameworks4 – 8Many reusable components available
    Python / JS / Modern Web8 – 12Mainstream development productivity
    Java / C# Enterprise10 – 15Includes architecture and standards overhead
    Embedded / C / C++15 – 25High debugging and testing cost
    Legacy System Maintenance20 – 30Comprehension and regression cost

Steps

  1. Identify function components: List all ILFs, EIFs, EIs, EOs, and EQs
  2. Assess complexity: Rate each component as Low / Medium / High
  3. Calculate UFP: Sum (count × weight) for all components
  4. Select conversion factor: Choose person-hours per FP based on technology stack
  5. Compute total effort: UFP × conversion factor
  6. Add buffer: A 15–30% management and risk buffer is recommended

Estimation Adjustment Factor Checklist

After completing the estimation, verify that the following factors have been accounted for:

Technical Factors

  • Technology stack familiarity (Is the team experienced? If unfamiliar, add 30–50%)
  • Technical debt (Poor legacy code quality? Add 20–40%)
  • Third-party dependencies (Unstable APIs? Missing documentation? Add 10–30%)
  • Performance / security requirements (Special non-functional requirements? Add 15–25%)

Team Factors

  • Team size (Communication overhead increases significantly above 5 people; add ~5% per person)
  • Personnel turnover risk (Key members may leave? Add 15–25%)
  • Parallel projects (Team context-switching across multiple projects? Add 20–30%)
  • Onboarding new members (New hires? Expect ~50% reduced efficiency for the first 2 weeks)

Process Factors

  • Requirements stability (Requirements likely to change? Add 20–50%)
  • Approval processes (Multiple layers of approval needed? Add 10–20%)
  • Deployment complexity (Multi-environment, multi-region deployments? Add 10–15%)
  • Compliance requirements (Audit or compliance processes? Add 15–30%)

Commonly Underestimated Work

  • Code review: +10–15%
  • Unit test authoring: +15–25%
  • Integration / E2E testing: +10–20%
  • Documentation: +5–15%
  • Bug fixing and regression: +10–20%
  • Environment setup and DevOps: +5–10%
  • Meetings and communication: +10–15%

Estimation Output Template

After the Agent completes the estimation, it should produce output in the following format:

## Estimation Report: [Project / Feature Name]

### Estimation Method: [PERT / T-shirt / FPA]

### Work Package Breakdown

| # | Work Package | O (person-days) | M (person-days) | P (person-days) | E (person-days) | σ |
|---|-------------|-----------------|-----------------|-----------------|-----------------|---|
| 1 | xxx         | x               | x               | x               | x.x             | x.x |
| 2 | xxx         | x               | x               | x               | x.x             | x.x |

### Summary

- Total expected effort: X person-days
- Total standard deviation: X person-days
- 68% confidence interval: X – X person-days
- 90% confidence interval: X – X person-days
- 95% confidence interval: X – X person-days

### Adjustment Factors
- [Factors considered and adjustments applied]

### Final Recommendation
- For internal planning: X person-days (90% confidence)
- For external quotes: X person-days (95% confidence)

### Risk Alerts
- [Key risk items and mitigation suggestions]

Calculation Tool

The scripts/estimate_calculator.py script supports numerical calculations for all three estimation methods:

# Three-Point Estimation (PERT)
python3 scripts/estimate_calculator.py --method pert \
  --tasks '[{"name":"Login Module","O":2,"M":3,"P":8},{"name":"Payment Module","O":5,"M":10,"P":20}]'

# T-shirt Size Conversion
python3 scripts/estimate_calculator.py --method tshirt \
  --tasks '[{"name":"Login Module","size":"M"},{"name":"Payment Module","size":"L"}]'

# Function Point Analysis
python3 scripts/estimate_calculator.py --method fpa \
  --components '[{"type":"ILF","complexity":"medium","count":3},{"type":"EI","complexity":"low","count":5}]' \
  --hours-per-fp 10

References

  • IFPUG (International Function Point Users Group) CPM 4.3.1
  • PMI PMBOK Guide — 6th Edition, Section 6.4: Estimate Activity Durations
  • Steve McConnell, Software Estimation: Demystifying the Black Art
  • Mike Cohn, Agile Estimating and Planning
Repository
zebbern/claude-code-guide
Last updated
First committed

Is this your skill?

If you maintain this skill, you can claim it as your own. Once claimed, you can manage eval scenarios, bundle related skills, attach documentation or rules, and ensure cross-agent compatibility.